Landscape Project Update

Hide Featured Image
true

 

Once the irrigation is turned on and we can start evaluating the system then we can start getting a good plan together. As of now we will most likely proceed in this order.

 

  1. 1st Evaluate irrigation – make all necessary adjustments. 2-5 days
  2. Work on the existing turf areas and demo and prep any new area for new turf area install new fescue where needed top dress and seed all old areas. 2-5 days
  3. Demo and prep all planting areas and provide a map of plant and shrub placement. Then start installing all plants. 2-4 days
  4. Provide a design map for rock areas to receive boulders and plants. Start install of these areas. 2-3 days
  5. Final Cleanup including removal of all old debris.

 

Landtech will need at least 1 if not 2 staging areas to keep our delivered material and equipment.

               

Please let us know if you have any questions. 

 

Rebecca Harris,

District Manager

 

614 N. Tejon St. 
Colorado Springs, CO 80903 
Office: (719) 447-1777  ext: 103

Direct: (719) 266-3189
Email: rebecca.h@wsdistricts.co

Website: www.WSDistricts.co